A building is handed over. Five weeks later the client notices damp spreading behind a bathroom wall. Under Swiss law as it stood until the end of 2025, that delay was a genuine danger: the Code of Obligations required notice of a defect to be given “immediately”, and the case law read that word strictly. A client who took a few weeks to decide whether the problem was serious enough to report could lose the whole warranty claim, not on the merits but on timing.

That is no longer the position. The partial revision of the Swiss Code of Obligations on construction defects entered into force on 1 January 2026, and it rewrites the rules that decide who pays for a defective building.

Sixty days instead of “immediately”

The central change is a fixed deadline. The revised Article 367 of the Code of Obligations gives the client 60 days from discovery of the defect to notify the contractor, and that period applies to visible and hidden defects alike.

The 60 days are also a floor: the parties cannot agree a shorter period, so a clause requiring notice within a fortnight, or “without delay”, no longer binds the client. Standard-form and bespoke construction agreements that narrowed the warranty catalogue were valid, and common; from 2026 they are not.

Repair is no longer negotiable

The revised Article 368 turns the client’s right to have defects put right at the contractor’s expense into a mandatory right for immovable works. Contractual exclusions and limitations of that right are now void.

The revision also confirms what the Federal Supreme Court had already developed in its case law: where the contractor fails to remedy the defect within the deadline set, the client may have the work done by a third party and recover the cost, without first obtaining authorisation from a court.

Five years, and no shorter

The limitation period for defect claims on immovable works stays at five years. Parliament debated doubling it to ten and rejected that, after sustained opposition from the contractors’ side. What changed instead is its character: under the revised Article 371 the five-year period is now relatively mandatory, meaning it cannot be modified to the client’s disadvantage.

Buying a recently built property

The reform does not stop at construction contracts. A new Article 219a extends the same logic to sales of real estate: the buyer has 60 days to give notice of defects, and where the building is still to be erected or was erected less than two years before the sale, the buyer can require the seller to remedy defects at the seller’s cost. Here too, the five-year limitation period cannot be cut back to the buyer’s detriment.

The target is a familiar Swiss market practice: off-plan and newly completed flats sold with warranty exclusions that left the buyer to chase subcontractors. Outside that two-year window, the ordinary rules on warranty exclusion in property sales still apply.

Releasing a builders’ lien gets cheaper

Alongside the Code of Obligations, the revision amended Article 839 of the Swiss Civil Code on the builders’ lien — the statutory mortgage a contractor can register against the property it has worked on. An owner can still avoid or remove the registration by providing sufficient security, and here the reform cuts the other way. Federal case law had required that security to cover default interest with no time limit at all; the revised provision caps it at the claim plus default interest for a maximum of ten years.

For developers that is a real reduction in the capital tied up to clear a lien, and it applies whatever the date of the underlying contract.

Which contracts are caught

The starting point is the date of signature: the new provisions apply to contracts concluded on or after 1 January 2026, so contracts signed earlier keep their warranty exclusions even if the work and the defects come much later. Two projects running side by side may therefore sit under two different regimes for years.

There are two qualifications, and both matter in practice:

  • the mandatory five-year limitation period is understood to reach into older contracts where the parties had agreed a shorter period that had not yet expired on 1 January 2026 — so a two-year warranty window in a 2024 contract may no longer hold;
  • the amended Article 839 CC on builders’ liens applies regardless of when the contract was concluded.

How far that first point reaches into existing contracts is not settled among Swiss commentators, and it is worth specific advice before relying on a short warranty period agreed under the old law.

What to review

The work is contractual rather than operational:

  • check construction and property-sale templates for warranty exclusions, shortened notice deadlines and reduced limitation periods: these clauses are now void in the covered cases;
  • confirm which live contracts were concluded before 2026, since the applicable regime turns on that date;
  • contractors should price in the mandatory rectification duty rather than assume it can be contracted away, and plan for a longer window in which defect notices can arrive;
  • developers offering security to release a builders’ lien should check the figure against the new ten-year cap on default interest, which applies to existing projects too;
  • parties using the SIA 118 standard conditions should note that its notice provisions were drafted around the old “immediately” rule and will need to be read, or amended, in light of the mandatory 60-day period.

The reform shifts risk towards the party that builds and sells. The documents that allocate that risk were mostly drafted on the opposite assumption, and they are the place to start.