A Flemish permit that survives a court challenge is worth considerably more than one that arrives quickly and is then annulled. That is the premise behind the Actieprogramma inzake rechtszekere en robuuste vergunningen — the action programme on legally certain and robust permits — which the Flemish Government approved on 19 December 2025 and which is now producing draft decrees at a steady pace.

For a company planning a plant, a distribution centre or a housing scheme in Flanders, the question is not whether procedures become shorter. It is where the risk of annulment moves, and who has to speak up and when.

Where the programme came from

The programme rests on the final report of the Gemengde Commissie Vergunningen, a mixed commission of government officials, academics and practitioners, which produced 45 recommendations. It was taken forward by Minister-President Matthias Diependaele and Minister Jo Brouns.

The work is grouped into three strands: regulatory initiatives, including decree amendments to optimise the modular environmental permit procedure and the planning instruments; practice-oriented initiatives, covering a culture of early dialogue, simplified norm books and training; and digital initiatives centred on the Omgevingsloket, the Flemish environment portal.

The decree that is still waiting

Underneath all of this sits a decree that has existed for over two years without applying. The Decreet van 17 mei 2024 amending the environmental permit legislation introduced the modular environmental permit procedure and a new instrument, the omgevingsbesluit. It was published in the Belgisch Staatsblad on 9 August 2024.

It is not yet in force. The administration is explicit that entry into force depends on amending the Omgevingsvergunningenbesluit and on the further development of the Omgevingsloket, and that no date is currently available.

“Modular” describes the design. Instead of the classic choice between the ordinary and the simplified procedure, the modules required are deployed according to the content and nature of the application. The omgevingsbesluit is a separate route intended to accelerate spatial impulse projects, works of public interest and business activities.

Rewritten before it ever applied

Rather than wait, the Flemish Government has reopened the text. A draft decree amending several decrees following the introduction of the modular procedure received a first approval in principle on 29 May 2026 and a second on 17 July 2026, and is awaiting the advice of the Council of State.

A second draft decree, approved in principle on the same July date, implements further parts of the action programme and amends the Gemeentewegendecreet. Its best-known element narrows the subdivision permit obligation and limits the regulatory effect of subdivision prescriptions and subdivision plans in time. A third draft, approved in principle on 26 June 2026, addresses the functioning of the Flemish administrative courts.

A right to talk before you apply

The first amending draft would anchor in the decree a right to pre-application consultation — vooroverleg — for every initiative taker, available on request and without formalities.

In practice many Flemish authorities already hold such meetings. Turning the practice into an entitlement matters mainly for larger or contested files, where the useful conversation is the one that happens before drawings are frozen and before an application fixes the terms of the debate.

Objections acquire a deadline

The more consequential shift concerns participation. The draft moves towards a single public inquiry per file at first instance, with one administrative appeal and one request for review, coupled with a duty on participants to raise their points during the procedure.

The direction of travel is that arguments not put forward in the permit procedure cannot be saved up for later use before the Raad voor Vergunningsbetwistingen, the Flemish council for permit disputes, and that a request for review must be exhausted before the council is approached at all. For an applicant that is welcome discipline. For anyone monitoring a neighbouring project, it is a reason to engage early rather than wait.

Sector advice stops being the last word

The draft also clarifies the role of advisory bodies. Their input is confined to their own field of expertise, and it is the permit authority that makes the final assessment of legality and desirability, with an obligation to give substantive reasons where it departs from an opinion.

That cuts both ways. A negative opinion is no longer a near-automatic refusal, but a permit granted against advice needs reasoning capable of withstanding review.

What to do while the drafts move

Nothing here is final law, and the modular procedure’s start date remains tied to an implementing decision and to the portal. Even so, several steps are already worth taking on any Flemish project:

  • build pre-application consultation into the project timetable, and minute what is discussed and agreed;
  • treat the public inquiry as the decisive moment for third parties, and record responses to objections in the file rather than at appeal stage;
  • check whether a site relies on old subdivision prescriptions, because their regulatory force is among the points being revisited;
  • in transactions, test permit assumptions against procedures that may change between signing and delivery.

A permit regime built around robustness rewards whoever assembled the better file. That work happens long before the first hearing.